Building HQ3,Canary Wharf South
Contractor: Canary Wharf Contractors Ltd
The 165m high core was Slipformed over a 14 week
period, working on a day shift only basis. A total of 7700 m3
of concrete was placed into the walls via a placing boom mounted
on top of the Slipform rig.
The average daily rate of slide was 2.54m
with a maximum rate of 3.2m being achieved. The specially engineered
Slipform rig not only carried the dynamic loads from the placing
boom, but included sufficient capacity to allow the storage of
up to 100 tons of materials and plant. The core walls were successfully
completed within the very tight tolerances required by Canary
Wharf Contractors.